Master Planning

  • Master Planning Overview

    [ Enterprise | Premier ] <script src="https://fast.wistia.com/embed/medias/q8wwee2yqj.jsonp" async=""></script> <...

    Read More >
  • Enable New Master Planning

    [ Enterprise | Premier ] How to Enable the New Master Planning Account Administrators now have the ability to enable the new Master Planning interf...

    Read More >
  • Master Planning: Resources

    [ Enterprise | Premier ] Overview The Master Planning page is divided into two main sections. The Resources List on the left side of the Master Pla...

    Read More >
  • Master Planning: Allocations

    [ Enterprise | Premier ] Overview The Master Planning page is divided into two main sections; to the right side of your resources and projects list...

    Read More >
  • Master Planning Filters

    [ Enterprise | Premier ] Overview Master Planning has several available filtering options, depending on whether you’ve grouped by Team Member or Pr...

    Read More >
  • Master Planning Display Preferences

    Overview The type of resource planning information that appears in the Resource List or on the Allocations Timeline—including how it's displayed—is...

    Read More >
  • Roles in Team Member View

    Overview When Master Planning is grouped by Team Member, the Resource List contains rows of unnamed resources and team members. Each resource row c...

    Read More >
  • Add a Resource to a Project

    [ Enterprise | Premier ] Step-by-Step How to Add a Team Member to a Project Hover over Planning on the left-side nav bar and select Master Plannin...

    Read More >
  • Edit a Resource

    [ Enterprise | Premier ] Overview Master Planning allows you to change the role of a team member assigned to a particular project; you can also cha...

    Read More >
  • Change a Resource to Named or Unnamed

    [ Enterprise | Premier ] Step-by-Step How to Change an Unnamed Resource to a Team Member Hover over Planning on the left-side nav bar and select M...

    Read More >
  • Master Planning: Show and Hide Resources

    Team members may belong to projects without being allocated or scheduled—either because they have yet to be assigned, are not working directly on t...

    Read More >
  • Delete a Resource

    [ Enterprise | Premier ] Step-by-Step How to Delete a Resource Hover over Planning on the left-side nav bar and select Master Planning. On the Mas...

    Read More >
  • Add an Allocation to a Resource

    [ Enterprise | Premier ] NOTE Master Planning automatically accounts for individual time off, scheduled weekends, and company holidays assigned vi...

    Read More >
  • Edit an Allocation

      [ Enterprise | Premier ] Step-by-Step How to Edit an Allocation in Master Planning Hover over Planning on the left-side nav bar and select Mas...

    Read More >
  • Delete an Allocation

    [ Enterprise | Premier ] Step-by-Step How to Delete an Allocation in Master Planning Hover over Planning on the left-side nav bar and select Maste...

    Read More >
  • Shift Allocations

    Available in: Enterprise and Premier If you have an upcoming project that needs to be pushed back a few weeks due to unforeseen circumstances, Mave...

    Read More >