Nesting Tasks

Available in: EnterprisePremierProfessionalTeams, and Free

You can capture the entire breakdown of your project and nest up to five levels of tasks, issues, deliverables, or milestones.

Nested-Task-List.pngUse additional levels of sub-items to organize your work with more granular detail. This allows you to capture all the necessary tasks that need to be completed for project success and completion.

Add-Subtask-Button.png
You can nest your tasks underneath others by either clicking the ‘Add Sub-Task’ button on a task or by using drag-n-drop.

How do I edit a top-level task's date?

The start and due dates of a task are based on the earliest start and due date of its subtasks. The dates of sub-tasks roll up to the dates of the top level task. Editing the dates of the sub-task will modify the dates of the parent item.

To change the date of a top level task you must first change the dates of the subtasks associated with the parent task. New dates will appear in the top level of the task.